
Water Treatment Plant Construction
Northeast Remsco Construction has worked with numerous Owners and Engineers to construct and upgrade both water and wastewater treatment plants in New Jersey and New York City. We have successfully completed work for public and private facilities and have been involved in Design- Build, GMP, and fixed price project delivery methods.
A Proven Treatment Plant Construction Process You Can Trust
Our team of experts work hand in hand with engineering and operations to ensure proper planning and execution to deliver the project the right way and on schedule. We self-perform the majority of the work and have our project management team on site to monitor quality and production while insuring that the work is done safely. We pride ourselves with providing creative solutions to extremely difficult deep and wet excavations and work in tightly congested existing facilities.
Our project resume includes state of the art membrane filter plants for both water and wastewater treatment, Odor control systems, DAF treatment and traditional treatment plant technologies, and have completed numerous bypasses of existing flows exceeding 80 MGD. We have converted sludge digester systems to combined heat and power generation to provide plants with alternative power sources and have installed cogeneration systems for landfill applications.
Treatment Plant Construction that Delivers Every Time
Northeast Remsco Construction has constructed and upgraded numerous water and wastewater treatment plants in NJ and NYC including state of the art membrane filter plants, traditional flocc/sed, and DAF treatment facilities. In addition, we have also completed treatment plant construction on numerous combine heat and power facilities in existing plants that run on digester or landfill gas.
Our team of experts self-performs the majority of our treatment plant construction work including excavation, piling, concrete, mechanical equipment, and piping installation. Our experience includes work for public and private facilities as well as design-build projects. Regardless of the job type, owner, specific needs or requirements of the treatment plant construction, or any other factor, Northeast Remsco Construction is here to help.
View Some of Our Treatment Plant Construction Projects
Park Avenue Wastewater Treatment Plant Upgrades
Upgrade to include granular activated carbon (GAC) treatment for removal of per- and poly-fluoroalkyl substances (PFAS) at the 12 million gallon per day (mgd) groundwater facility. Major work included: aggregate piers, underslab carbon steel piping, backwash waste tank, mechanical piping and equipment, 20 GAC vessels with carbon media, 5kV switchgear installation, and diesel generator installation.
Location: South Plainfield, NJ
Date: Completion November 2023
Owner: Middlesex Water Company
Sayreville Pump Station
Flood Mitigation and Permanent Restoration of Sayreville. The treatment plant construction project included improvements to the electrical systems and the construction of a perimeter flood wall that was approximately 1,700 feet long and constructed with a designed top elevation of 21 feet above sea level.
Location: Sayreville, NJ
Date: 2017-2021
Owner: Middlesex County Utilities Authority (MCUA)
Gowanus Facility Upgrade
Install three new submersible pumps to replace the original single propeller configuration, and rehabilitate portions of the 1.15 mile tunnel. The new interchangeable pumps will eliminate shutdowns at low tide and will virtually eliminate shutdowns for maintenance. In addition, the tunnel’s flow capacity will increase from 154 million gallons per day (mgd) to 215 mgd. Major facility upgrades will result in improvements to the water quality of the canal and reduce sewer discharges.
Location: Brooklyn, NY
Date: 2009- 2019
Owner: NYC Department Of Environmental Protection
Oak Glen Water Treatment Plant Expansion
Installed a more robust dissolved air flotation (DAF) clarification system. The entire DAF recycle system (pumps, strainers, piping, saturators and compressors) was updated to be a single system for a total plant design flow of 15 MGD.
Location: Farmingdale, NJ
Date: 2016-2018
Owner: Owner New Jersey American Water Co.
Let us know how we can help you with your project?
